Shortfall of $74,134 on the wastewater project in Barriere

Unexpected $142,650.00 paid due to archaeological find work stoppage related

Wastewater Project Budget Update: The grant application that was submitted in 2010 included an estimated budget that was based on a basic design and the prices of the day.  The tenders and cost of the work that has been completed to date are for the most part in excess of these estimates. In the case of the collection system, the scope of the project was pulled back to deal with the increased pricing once the detailed design estimates were established. When the tender was awarded for the collections, effluent and Septage Receiving Station the money allotted to the wastewater plant itself was capped at the amount remaining. The capital improvements made to affected roads and water infrastructure in the areas of excavation are not included in this budget.

The Septage Receiving Station budget was estimated at $1,170,000.00. To date the costs are at $1,179,572.77.  The only remaining anticipated cost is to purchase the required filter box for approximately $65,000.00, bringing the total anticipated cost of this component to $1,244,572.77.  The Septage Receiving Station project will be $74,572.77 over the 2010 estimated budget.

The Sewer Collection portion of our project had an anticipated 2010 budget of $2,477,000.00.  We are estimating the total owing to LNB is $95,000.00 and the total that will need to be spent on inspection and communications costs to be $18,000.00 for a total project cost of $2,517,709.13 – over budget by $40,709.13.

In our grant submission the Effluent Disposal costs were estimated at $440,000.00.  To date we have paid $270,000.02 and anticipate an additional $15,000.00 cost of Municipal Wastewater Regulations (MWR) documentation requirements for a total cost of $285,000.02 – under budget by $154,999.98.

The Solar Aquatics Wastewater Plant component of this project had an estimated grant application budget of $2,613,000.00.  This portion of the project saw a significant change to the hot water heating system approved after the project began.  $240,067.12 in solar-related costs were removed from Eco-Tek’s budget and directed towards the purchase of a biomass boiler system from Fink Machine at a cost of $218,540.00. In addition to the equipment supplied in the boiler contract, associated costs of $180,740.05 have been expended for a larger container that will house the boiler and the back-up genset for the plant, a chip storage building and the related concrete foundations and pads.  This change added just over $159,000.00 to the cost of the wastewater plant portion of the project.  This component of the project is currently over budget by $113,852.81.

To date the entire project plus anticipated costs total $6,774,137.73, compared to the 2010 estimated budget amount of $6,700.000.00 – an overall shortfall of $74,134.73. A very significant cost that was not anticipated is $142,650.00 that needed to be paid as a result of a work stoppage related to an archaeological find at the beginning of the winter season last year.

The Collection system was determined to be substantially complete on November 5. A one-year maintenance period is now in effect.  This will expire on November 5, 2016.  This means that any deficiencies that are discovered must be corrected by LNB up until November 5, 2016.

The lift station commissioning was successfully completed on November 5.  As of November 5 the lift station was set to function in “auto” mode based on water levels.  The system is functioning as intended.

The 10 per cent Builders Lien holdback will be released 55 days after substantial completion (December 30, 2015). TRUE will provide documentation to the District identifying when to release this holdback.

Final project quantities are being reviewed presently by LNB.  LNB will soon (last week of November) be providing documentation which identifies agreement with TRUE’s final quantities and stating that LNB will not be submitting any further claims for works completed under this project.  Once this documentation has been received, TRUE will issue the final progress draw to the District for payment.

A $12,000 deficiency holdback will be retained from LNB associated with two asphalt repair deficiencies on Yard Rd in front of the Station House.  LNB is attempting to schedule this repair this fall, however the weather window needed for paving may have passed for the season.  The $12,000 deficiency holdback will be retained by the District until such time as the asphalt repairs have been completed, which may be spring 2016.

Next steps: TRUE will finalize the record drawings and service cards for the project.  Also, there should be a general inspection completed in key manholes in spring 2016 as the groundwater table begins to rise.  We want to ensure that these remain watertight.  If the District begins to see infiltration of groundwater then LNB will have to come back to correct.

It was found during testing at the Septage Receiving Station (SRS) that a couple of the valves were incorrectly installed. This has been fixed. The generator was commissioned successfully on November 18.  The SRS facility can now function during a power outage.

ECO-TEK continues to work on completing the Solar Aquatics System (SAS) although weather is now again playing a major factor in its timely completion.

 

Just Posted

Okanagan Lake (File photo)
Thompson-Okanagan ready to welcome back tourists

The Thompson-Okanagan Tourism Association expects this summer to be a busy one

teaser
Dynamic drives and pitiful putting helped even the score

Another Ladies’ Night has come and gone. This season is passing by… Continue reading

Tim Schewe
Drivesmart column: Traffic cop humour

He demands to know what sort of device had been used to measure his speed

(L-r) Cody Lee with six-year-old daughter Paisley, and Joshua Burleigh with his seven-year-old son Noah are extremely thankfull to Heffley Creek residents and First Responders for the help they received after their canoe capsized in rapids on the North Thompson River on Sunday, June 13. (Facebook photo)(L-r) Cody Lee with six-year-old daughter Paisley, and Joshua Burleigh with his seven-year-old son Noah are extremely thankfull to Heffley Creek residents and First Responders for the help they received after their canoe capsized in rapids on the North Thompson River on Sunday, June 13. (Facebook photo)
North Thompson River canoe trip almost ends in disaster

‘Only way I managed to get us to shore was the thought of not letting my boy drown’

A for sale sign is shown in by new homes in Beckwith, Ont., just outside Ottawa, on Wednesday, Jan. 11, 2018. THE CANADIAN PRESS/Sean Kilpatrick
Thompson-Okanagan population grew despite COVID-19: report

The Chartered Professional Accountants of BC said there are 8,462 new residents in the region

Maxwell Johnson is seen in Bella Bella, B.C., in an undated photo. The Indigenous man from British Columbia has filed complaints with the B.C. Human Rights Tribunal and the Canadian Human Rights Commission after he and his granddaughter were handcuffed when they tried to open a bank account. THE CANADIAN PRESS/HO-Heiltsuk Nation, Damien Gillis, *MANDATORY CREDIT*
VIDEO: Chiefs join human rights case of Indigenous man handcuffed by police in B.C. bank

Maxwell Johnson said he wants change, not just words, from Vancouver police

Tk’emlups te Secwepemc Chief Rosanne Casimir stands outside the former Kamloops Indian Residential School after speaking to reporters, in Kamloops, B.C., on Friday, June 4, 2021.THE CANADIAN PRESS/Darryl Dyck
Kamloops chief says more unmarked graves will be found across Canada

Chief Rosanne Casimir told a virtual news conference the nation expects to release a report at the end of June

A woman wears a vaccinated sticker after receiving a COVID-19 vaccine at a vaccination clinic run by Vancouver Coastal Health, in Richmond, B.C., Saturday, April 10, 2021. THE CANADIAN PRESS/Jonathan Hayward
B.C. ranks among highest in world in COVID-19 first-dose shots: health officials

More than 76% of eligible people have received their 1st shot

A screenshot of the First Peoples Cultural Councils First Peoples’ Map. (First Peoples Cultural Council)
Online resource blends B.C.-Alberta’s Indigenous languages, art and culture

Advisor says initiative supports the urgent need to preserve Indigenous languages

An artists conception of the new terminal building at the Pitt Meadows Regional Airport.
Air travel taking off in B.C., but lack of traffic controllers a sky-high concern

There will be demand for more air traffic controllers: Miller

Canadian Armed Forces experts are on their way to North Vancouver after a local homeowner expressed worry about a military artifact he recently purchased. (Twitter DNV Fire and Rescue)
Military called in to deal with antique ‘shell’ at North Vancouver home

‘The person somehow purchased a bombshell innocently believing it was an out-of-commission military artifact’

Phil McLachlan/(Black Press Media
Man shot at Kamloops shopping centre

The man is believed to be in stable condition

Amy Kobelt and Tony Cruz have set their wedding date for February, hoping that more COVID-19 restrictions will have lifted. (The Macleans)
B.C. couples ‘gambling’ on whether COVID rules will let them dance at their wedding

Amy Kobelt and Tony Cruz pushed back their wedding in hopes of being able to celebrate it without the constraints of COVID-19

Most Read