Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepencies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

A second wave of COVID-19 is probable, if history tells us anything

B.C.’s top doctor says that what health officials have learned this round will guide response in future

Upper Clearwater naturalist helps name national lichen

The votes are in for Canada’s proposed national lichen and the Star-tipped… Continue reading

Celebrations continue for Tsilhqot’in Nation after court victory against Taskeo Mines Ltd.

Supreme Court of Canada upholds 2014 decision rejecting New Prosperity mine on May 14, 2020

38 ladies had plenty of room to social distance

A couple of years ago hubby and I purchased 600 (yes, 600)… Continue reading

Invasive Mussel Defence program launches in B.C.

Boat inspection stations are now open at various locations throughout the province… Continue reading

B.C. mom’s drug-pricing petition on behalf of son garners thousands of signatures

Petition geared to gaining access to new medicines drew support of Chilliwack-Hope MP Mark Strahl

‘Paralyzed by fear’: B.C. woman details anxiety, grief at Italian relief hospital

Sheila Vicic spent two months in Italy as the country grappled with COVID-19

Dr. Bonnie Henry given new name in B.C. First Nation ceremony: ‘one who is calm among us’

The provincial health officer was honoured in a May 22 ceremony at elementary school in Hazelton

CAMH survey looks at binge-drinking, financial anxiety during COVID

Alcohol may be used as a coping mechanism for those whose careers may have been sidelined due to the pandemic

Half of Canadians say governments are hiding something about COVID-19: poll

More than a third of people believe the virus was created in a lab

Kelowna man charged with harming a hamster

The 20-year-old Kelowna man faces several animal cruelty charges

High tech fish transport system set up to ‘whoosh’ salmon past Big Bar landslide

Fish will spend roughly 20 seconds inside the system, moving at roughly 20 metres per second

Trudeau to seek 10 days of paid sick leave for Canadian workers, says talks are ongoing

Paid sick leave is key to keeping COVID-19 spread under control, prime minister says

Most Read