Diversion tunnels have been completed to redirect the Peace River during low water this summer, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

Diversion tunnels have been completed to redirect the Peace River during low water this summer, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

Open letter urges B.C. to pause work at Site C dam to review costs, geotechnical issues

Dam has been affected by possible COVID-19 delays

A letter addressed to NDP Leader John Horgan is urging the province to halt the construction of the Site C dam while geotechnical issues are investigated.

The open letter, which includes signatories such as former BC Hydro CEO Marc Eliesen, Chief Roland Willson of the West Moberly First Nations and 16 other former CEOs, scientists and Indigenous leaders, says that the “problem-plagued” project needs to stop construction.

“The Site C project is years away from completion, is mired in problems that may be unfixable, and confronts new, potentially horrendous cost over-runs,” the letter states.

The letter cites geotechnical problems revealed in July, when BC Hydro CEO Chris O’Riley wrote of “a project risk” to do with the right bank. O’Riley said that “investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas.”

The CEO’s letter also cited financial hurdles brought about by the COVID-19 pandemic. Prior to the worldwide health crisis, the first generating unit of the Peace River dam was scheduled to go into service in late 2023, with a final in-service date in 2024.

“While we remain on schedule to achieve river diversion in 2020, there is uncertainty with the project’s schedule and in-service date. This is primarily due to our ability to re-start and accelerate work that was halted due to the pandemic,” O’Riley wrote in July.

Monday’s (Sept. 28) open letter asks the government to “immediately suspend all construction activities at the project” while giving Site C special advisor Peter Milburn, a former B.C. government bureaucrat with a background in civil engineering, time to accomplish three tasks.

The open letter’s signatories want Milburn to appoint a panel of three professionals with no link to Site C to do geotechnical assessment. Secondly, the letter asks for that information to be public prior to the government making a decision to restart the project.

“This is crucial because to date the public’s trust in the Site C project has been eroded by a lack of transparency,” the letter states. The last ask is for the public to get a “full accounting” of the costs to date associated with Site C, as well as of the upcoming costs required to complete the project.

The cost of the Site C Dam was pegged at $7.9 billion in 2011 but has grown to $10.7 billion. The dam has also been the subject of legal battles, with the Prophet River First Nation settling one in early August.

READ MORE: Agreement between province, BC Hydro, First Nation, ends legal fight over Site C

READ MORE: BC Hydro’s Site C set back by COVID-19, foundation changes


@katslepian

katya.slepian@bpdigital.ca

Like us on Facebook and follow us on Twitter.

Want to support local journalism during the pandemic? Make a donation here.

CoronavirusIndigenousSite C

Just Posted

File photo
BREAKING: Fuel tanker fire closes Highway 24

Emergency crews are on scene on Highway 24 at Cartwright Road.

Residents line up outside the Vernon Recreation Complex for their COVID-19 vaccine Saturday, June 5. (Jennifer Smith - Morning Star)
No appointments necessary for first dose COVID-19 vaccine: Interior Health

People can just show up at clinics, register on the spot and get the shot

(TNRD Library)
Let the mystery of the Summer Reading Club begin

Are you ready to ‘Crack the Case’ at the Barriere Library?

(Metro Creative photo)
Gardeners of all ages invited to enter 2021 NT Fall Fair contests

The North Thompson Fall Fair Drive Thru scheduled for Saturday, Sept. 4,… Continue reading

Milsom Lodge was built in the East Barriere Valley when the Milsom brothers purchased two parcels of land in 1911, DL 2323 and DL2324. (Milsom’s photo)
The Milsom Lodge: The mansion, the ballroom, the history

“At the turn of the century, when so many families were leaving… Continue reading

Canadian Prime Minister Justin Trudeau participates in a plenary session at the G7 Summit in Carbis Bay, England on Friday June 11, 2021. THE CANADIAN PRESS/Adrian Wyld
Canada donating 13M surplus COVID-19 vaccine doses to poor countries

Trudeau says the government will pay for 87 million shots to be distributed to poor countries

Premier John Horgan speaks as provincial health officer Dr. Bonnie Henry, right, and health minister Adrian Dix look on during a press conference to update on the province’s fall pandemic preparedness plan during a press conference from the press theatre at Legislature in Victoria, Wednesday, Sept. 9, 2020. THE CANADIAN PRESS/Chad Hipolito
B.C. officials to provide details on Step 2 of COVID reopening plan Monday

Step 2 could allow for larger gatherings and a resumption of recreational travel

Indigenous Services Minister Marc Miller is seen during a news conference, Wednesday May 19, 2021 in Ottawa. THE CANADIAN PRESS/Adrian Wyld
Indigenous child-welfare battle heads to court despite calls for Ottawa to drop cases

Feds are poised to argue against two Canadian Human Rights Tribunal rulings

The Great Ogopogo Bathtub Race has been held in Summerland as a fundraising event. Do you know which Canadian city introduced this sport? (Black Press file photo)
QUIZ: A summer’s day at the water

How much do you know about boats, lakes and water?

Two-year-old Ivy McLeod laughs while playing with Lucky the puppy outside their Chilliwack home on Thursday, June 10, 2021. (Jenna Hauck/ Chilliwack Progress)
VIDEO: B.C. family finds ‘perfect’ puppy with limb difference for 2-year-old Ivy

Ivy has special bond with Lucky the puppy who was also born with limb difference

A million-dollar ticket was sold to an individual in Vernon from the Lotto Max draw Friday, June 11, 2021. (Photo courtesy of BCLC)
Lottery ticket worth $1 million sold in Vernon

One lucky individual holds one of 20 tickets worth $1 million from Friday’s Lotto Max draw

“65 years, I’ve carried the stories in my mind and live it every day,” says Jack Kruger. (Athena Bonneau)
‘Maybe this time they will listen’: Survivor shares stories from B.C. residential school

Jack Kruger, living in Syilx territory, wasn’t surprised by news of 215 children’s remains found on the grounds of the former Kamloops Indian Residential School

A logging truck carries its load down the Elaho Valley near in Squamish, B.C. in this file photo. THE CANADIAN PRESS/Chuck Stoody
Squamish Nation calls for old-growth logging moratorium in its territory

The nation says 44% of old-growth forests in its 6,900-square kilometre territory are protected while the rest remain at risk

Most Read